On your visit to the Club over the Christmas holiday you will notice that a building site compound has been set up adjacent to the Club marquee.
This is the compound set up by Jones Bros - the contractor appointed to undertake the marine works as part of the Academy project.
They will start work in the New Year and the first stage is to construct a bund located to the west of the marina. This work is expected to take about four weeks.
The next stage in early Febuary is to start on the dredging work - starting with the new basin for the Academy visitor and event pontoons.
When the basin has been completed the dredger will then proceed to dredge under the Hafan marina pontoons. At the same time work will start on the new quay wall - adjacent to the new basin.